News for Neighbors
Big WindowsTOURS! The Old Town School is pleased to offer noon tours of the new building construction site. Get an inside view of the building-in-progress – its acoustically designed classrooms, spacious dance studios and flexible music and dance hall. Tour capacity is limited, so an RSVP is required – along with closed-toe shoes. Email RSVP@oldtownschool.org with your name, number of people and a date, below. Tours are available at 12 noon on these dates: All tours start promptly at 12 noon and last about 25 minutes. Meet inside the lobby at 4544 N. Lincoln at 11:55am. Support our building campaign now. Your support will be matched dollar-for-dollar thanks to our $200,000 Board Challenge! Progress The new building was designed to echo the architecture of the School’s existing building, with its tall windows and black terra cotta tiling. These effects will be achieved partly by steel lintels that are being installed ahead of the brickwork on the front. Steelworkers are working on the lintels now, working off of the platforms in the front. So sparks are flying again! Masons will use the same platforms to work their way up the face with brick. As the interior is built out, there is less and less space to work with inside. Along with lintels being lifted and the front stair base delivered and dragged down Lincoln Avenue, drywall is being delivered through side windows on the second floor. This complex array of street and alley activity will continue for the next couple of weeks. The Old Town School expects to open the new building in January, 2012. Filed under: Uncategorized by Gail | August 30, 2011 | Comments (1) Chasing Framers – Construction Sequencing 101Construction language provides some exquisite phrasing. Some phrases help visualize the whole process. “Chasing Framers” describes the process of putting up the skeletal, metal wall studs (framers) while the electricians follow behind, wiring everything before the dry wall goes up. Over the next four weeks, ductwork, HVAC piping, wall framing and electrical wiring will precede the next stage of drywall work. All of this interior work goes on while the masons build exterior (and interior) walls. The exterior walls are brick and a kind of corrugated steel on three sides. Coordinated carefully, “swing stages” allow crews working on the exterior to pace their work from the bottom up: brick goes first, then the crews install the corrugated steel. If you look at the south wall, much of the corrugated steel has been installed. The front facade will be brick, big windows and art. A little bit of the facade design can be seen now on the north side where Dreamtown meets the new building. The main facade part of the job will materialize over the next month. The interior of the new building is being constructed from the third floor down to the first so crews can keep moving and stay out of each other’s way. The first floor is last, partly because the space that will contain an ornamental glass staircase is being used as a staging area for the masonry operation, and partly because we don’t want to put in glass until we’re mostly done! Filed under: Uncategorized by Gail | June 28, 2011 | Comments (0) Bricks, Mortar, Sheetmetal, StudsMasons, Electricians and other crews were back on site as of Monday, June 6. Work has proceeded since then on ductwork, pipes, cinderblock, mortar, conduit, and all of the elements of a building that are mostly invisible once open to the public. For the next two or three weeks, the job focuses on masonry and ductwork. Exterior walls will go up as the building becomes enclosed. “Swing stages” are hanging off the outside of the building as some walls are built from the outside, some from the inside. We’re also expecting a major delivery of heavy rooftop mechanical equipment within the next two weeks. The photo here is on the second floor, looking into the dance hall/ performance space on Monday, June 13. The shell of the room is taking shape! The room shape to the right will house much of the equipment for the hall. Strike News: Since June 6, the Sprinkler Fitters had not yet settled their strike, but pickets were no longer on site. They apparently reached an agreement yesterday pending member ratification, and were not picketing anywhere as of midnight, according to their website. Filed under: Uncategorized by Gail | June 15, 2011 | Comments (0) Picket Line Day 3It’s June! The Old Town School and a number of other construction sites are being picketed by Sprinkler Fitters Local 281. A dozen workers or so picket until noon (the group in the picture is part of the picket line) then take their sign and camp chairs and leave the site. Other trades won’t cross the picket line, of course, and can’t start work after noon. Most of the other trades negotiated contracts last year, but the Sprinkler Fitters’ contract ran out May 31. The Fire Protection subcontractor for the Old Town School project, Nova Fire Protection, has an agreement to have the National Fire Sprinkler Association Contractors’ Negotiating Committee negotiate a contract with the Union. So that’s how it works. While this goes on, there’s not going to be much progress in actual construction. Work on the other side of the street — fundraising, planning the opening, planning for the Folk & Roots Festival, Summer Camp, classes for the summer and new programs for 2012 — continues. Filed under: Uncategorized by Gail | June 3, 2011 | Comments (0) Framing, Fireproofing and Ductwork – Quack!This week: Through May 20 Next Week: May 23 – May 27 Filed under: Uncategorized by Gail | May 18, 2011 | Comments (1) April ShowersThe rain is slowing down some of the crews, but work proceeds on the new building. This latest picture shows both the radiant heat coiling that will make for a warm and comfortable — and energy efficient – lobby and the concrete mostly poured for the second floor. That green mat holds the coils in place and helps insulate. The orange cable is the coil itself. On the second floor you can see the outline of the dance hall/performance space. It’s the underlying frame and base for the sprung-wood dance floor that will top it. Activities for the next couple of weeks: Filed under: Uncategorized by Gail | April 27, 2011 | Comments (1) Crane Pickers – week of 4.18.11Yes, that’s a crane in the city parking lot. With the steel up, foundation complete and masonry started, it’s the way to get the heavy roof curbs and other elements to the site without This crane picks materials off of the trucks and moves them down the alley to the roof of the new building. They tried it last week, but it was too windy to be safe. So today (Monday) and possibly tomorrow, there will be a crane in the city lot during work hours (8am to 4:30pm). Filed under: Uncategorized by Gail | April 18, 2011 | Comments (0) Iron Workers are Rockin’Structural steel is up — these guys are detailing right now, which means making sure the pins and rivets and whatever in the steel hold. There’s been a lot of noise while this happens, but street blockage is over except for materials deliveries, and the noise from riveting, detailing and soldering will be done by the end of the week. Photo Op: A few days ago we handed over guitars, a mandolin, a ukulele and harmonicas to the Iron Worker crew, and took this picture before work started with the crane. At least two of them play — can you guess which? The rock and roll jokes were free-flying as Erin English and Andy Moir worked on the roof of Lincoln Avenue West to try and capture the moment. Credit for this photo goes to Erin English. Construction Progress: Filed under: Uncategorized by Gail | April 1, 2011 | Comments (0) Structural Steel Almost FinishedThis week’s work involves delivery of the last of the steel and more detailing. Today, Monday, three steel deliveries are expected. Next week, along with detailing, we’ll be pouring concrete floors and finishing the foundation walls around the steel. It’s going to be a little tight on Lincoln Avenue this week during the working hours 8:00 AM to 4:30 PM. The big crane will leave the site and a smaller crane will work from Lincoln, getting the last of the steel up and in place. This means the sidewalk will be closed for a few days, and Lincoln will be down to one lane, with crews directing traffic, during the day. We sincerely appreciate your patience in the short term, and hope you share our excitement for what’s to come! Filed under: Uncategorized by Gail | March 14, 2011 | Comments (1) Construction: Week of 2.28.11DETAILING « Read more » Filed under: Uncategorized by Gail | February 27, 2011 | Comments (0) Classes
ConcertsSupportMusic StoreResourcesAbout Us |